Leadership Update · October 2026 · Reply All EnergyFloor 16 Technologies
Lead · Monthly update

Leadership Update: October 2026

Reply All Energy Inc. · For the leadership meeting on November 3

Prepared forPrepared byDateStatus
Leadership team
Chair: Ravi Menon, CEO
Floor 16 TechnologiesOct 30, 2026No. 4 · Issued

October closed the license review and the security baseline: $34,000 a year in cuts approved, and every account now signs in with MFA. One decision is needed this month: Microsoft seat counts, by November 24.

$34Ka year in license cuts approved; the first $2,652 stops October 31
100%of accounts on MFA, up from 71% in September
61%Microsoft Secure Score, up from 48%
2 of 3first-quarter items done; the third finishes in November

What shipped in October

  1. License review delivered October 14 and approved October 20: 13 lines, $34,224 a year.Grace Liu · Floor 16
  2. Zoom and Calendly cancelled. Teams and Bookings do the same jobs.Operations
  3. MFA on all 70 accounts. Four shared admin accounts replaced with named ones.IT provider
  4. Renewal calendar live: 27 contracts, each with a notice date and an owner, reminders 45 days ahead.Floor 16

Next, in November

  1. Microsoft seat counts to the reseller ahead of the January 1 renewal.Decision 1 below · Dec 1
  2. Smartsheet cancelled before its November 30 renewal.Notice by Nov 15
  3. Two partner folders moved from Dropbox to SharePoint guest access.IT provider · by Dec 10
  4. Conditional access switched on, which finishes the security baseline.IT provider · Nov 20
  5. AI boundary check scoped and quoted for January.Floor 16 · Nov 20

Roadmap progress

Q1License review
Done Oct 20
Q1Renewal calendar
Done Oct 24
Q1Security baseline
Nov 20
Q2AI boundary check
Starts Jan 4
Q2Finance AI pilot
Starts Feb 1
DoneIn progressLeft to doPlanned, not started

Decisions needed

#DecisionWe recommendOwnerBy
1Microsoft seat counts for the January 1 renewalE3 70, Copilot 10, Visio 4, and no licenses on shared mailboxes. Saves $10,728 a yearGrace LiuNov 24
2The AI pilot teamFinance: ten people, and month-end hours that can be measured before and afterRavi MenonNov 17
3Second-quarter budget$14K–21K for the boundary check and the pilot, as in the roadmapGrace LiuDec 8

Risks

RiskIf it happensWhat we are doingOwner
At risk
File server warranty ends June 30
A $28K replacement if the Move slips past JuneScan booked for February, Move in April and MayHannah Lee
Watch
The accounting feed is known by one person at the IT provider
A broken feed could stall month-endWritten runbook requested by December 15IT provider
Watch
15 unused Copilot seats paid through December 31
About $900 more before renewal. There is no early exitReduced at renewal, decision 1Grace Liu
Contractors still on SlackMoving them now would cut them off mid-projectReview in Q2, with Teams shared channelsKofi Mensah

The numbers

MeasureSeptemberOctoberTarget
Software spend, annual run rate$160,200$157,600$126,000 by Sep 2027
Paid seats unused in 90 days23%22%Under 7%
Accounts with MFA71%100%100%
Microsoft Secure Score48%61%70% by March
IT tickets open more than five days94Under 3
Backups test-restored011 a month
Floor 16 retainer hours used16 of 1615 of 16Planned a quarter ahead
Sample on a made-up company. Figures are scenario numbers, rounded. Real updates use the client's own numbers, every month, on one page.